Steam Turbine standard operating procedures (SOPs)
Lube oil system operation
Pre-checks
• Ensure lube oil tank level is normal • Ensure lube oil pumps are healthy to operate
• Ensure lube filter & cooler are in service
• Ensure lube oil inlet and outlet valve provided at
filters & coolers are open Ensure cooling water inlet & outlet valves
provided for oil coolers are in closed condition
• Ensure suction & discharge valve of the pumps are in opened condition
Operation
. Start the oil pump (AOP)
• Ensure no abnormal sound & vibrations . Observe the discharge pressure
• Ensure header pressure is normal, if not adjust
with PRV or recirculation valve . Check the oil filter DP, if high change over the
filter
. Check overhead oil tank is getting filling
• Ensure lub oil is supplying to each bearing & adjust the oil pressure to each bearing as per
desired requirement . Maintain the oil temperature by adjusting
cooling water inlet & outlet valves.
Note: Keep open cooling water inlet valve 100% open & adjust the temperature by adjusting outlet valve
• Ensure the over head oil tank is full Keep stand by lube oil pump & EOP ready
Barring gear operation
• Ensure lube oil system is in service and oil is circulating at the bearings at a desired pressure
• Ensure barring gear motor is healthy to start & its all interlocks are in place
Engage the barring gear clutch . Start the barring gear motor
Observe the rotor is rotating at barring speed without increase in bearing vibrations & temperature
• Ensure there is no any abnormal sound
Cooling water system operation Pre-checks
• Ensure the cooling tower level is normal • Ensure cooling water pump is healthy to operate
& their protections & interlocks are in place
• Ensure cooling water pump (MCWP) suction
valve is open & discharge valve is closed
• Ensure all the field instruments are healthy & inline
• Ensure surface condenser inlet & outlet cooling
water line valves are open • Ensure Condenser water box vents are open
• Ensure cooling tower inlet cooling water line
valves are open
Operation
• Start the pump from DCS at 70% RPM
Open the discharge valve slowly • Observe discharge pressure is increasing
gradually
• Ensure the pump's vibration & bearing
temperatures are normal • After venting air from condenser water box
close the vent valves ⚫ Observe cooling water is falling in cooling water
• Increase the pump's speed as per requirement ⚫ Note down cooling water inlet & outlet water
temperature of condenser
. Start cooling tower fans one by one as per
requirement
Condensate system operation
• Ensure the hot well level is adequate. Otherwise make the hot well level with DM water
• Ensure the CEP is healthy & its all interlocks are in place
• Ensure pump's suction & discharge valves are open
• Ensure ejector & gland sealing steam condenser inlet & outlet cooling water line valves are open . Start the pump, ensure the water will flow from
ejector & Gland steam condenser (GSC)
• Ensure gland steam outlet control valve to deaerator is close & cooling water is recirculating through recirculating control valve
• If the hot well level increases, then GSC discharge valve can be opened
. Once the Turbine comes into line,GSC outlet control valve should be kept in auto mode to maintain hot well level
• Vacuum pulling & Vacuum killing
• Pre-checks
• Ensure auxiliary steam is available at desired pressure and temperature . Ensure vacuum breaker valve fitted on steam
condenser is closed • Ensure cooling water is circulating in the condenser and the turbine gland is charged fully
at 0.1 kg/cm2
• Ensure live steam line to ejector steam lines
drain are kept open • Ensure Hogger & main ejectors steam and air
valves are in closed condition
Vacuum pulling through hogger ejector
⚫ Charge the main steam line to ejector steam &
temperature control valve
• Ensure the rated pressure (10 kg/cm2) and temperature (220 deg C) for ejector vacuum pulling
. Once the rated parameters are reached open the steam valve of starting or hogger ejector . Observe the steam is vented to the atmosphere
⚫ Then open the ejector airline valve
• Observe vacuum inside the condenser increasing slowly and will reach 60 to 70% of rated vacuum within 20 minutes
SOP to put main ejector into line
• Ensure CEP is running
• Ensure cooling water inlet and outlet valves of
main ejector which is to be taken into line . Vent out air from water box of the ejector
• Then open the drain valve of inter condenser and after condenser of ejector
. Open the steam valve of after condenser ejector • Open the steam valve of inter condenser ejector
. Observe the condensate is drained out from both the condensers
Slowly open the air valve & observe the vacuum
is increasing
• When vacuum reaches rated, then stop the hogger or starting ejector
Vacuum killing or Taking out of main ejector
. Close the air valve of the ejector
. Close the steam valve of inter condenser
. Close the steam valve of after condenser
. Close the drain valves of after & inter condensers
. Close the cooling water inlet & outlet valve once the ejector is cooled
Wednesday, January 18, 2023
SLOP BOILER OPERATING PROCEDURE
SLOP FIRED BOILER STARTING PROCEDURE:-
Pre-checks
• Ensure DM water storage tank, feed tank & Deaerator level are normal
• Ensure availability of start up fuel (wood) & main fuel (coal) and power supply with DG backup
• Ensure maintenance & trial runs (healthiness) of all equipment including fuel handling, ash handling/ auxiliaries, motorized valves, actuators, control valves and PRDS controls are completed successfully
• Ensure that all interlocks / protection and controls are checked & taken in line.
• Ensure expansion pointers are cleaned & tramps
are in good condition.
• Ensure Boiler manholes and flue gas path system manholes are boxed up.
• Ensure availability of chemical dosing system and
readiness of drum level gauge glass with
illuminator assembly.
• Ensure availability of cooling water, instrument air and service air.
• Ensure Coal bunker is filled with required level
. Ensure all rotary air lock valves of evaporator, economizer & bag filters are open
• Ensure healthiness of all dampers and keep them
in open/close marked positions as per requirement • Open all air releases/vent valves in boiler drum and open super heater header drains and its vent valves.
• Ensure all boiler bottom ring header drains, blow down valves and main steam stop valves including its bypass valves are closed.
• Ensure Boiler feed pump's bearings oil level normal, minimum recirculation, balancing leak off valves & suction valves are open, cooling water pressure normal.
Boiler start up
. Start the ACW pump, Instrument Air & Service Air Compressor
• Start BFP from control room. Ensure suction pressure, balancing pressure & discharge pressure normal. Bearing temperature & Vibrations normal. Ensure motor draws current normal & sound normal. Shut the BFP immediately if any abnormal condition and check thoroughly before restart.
. Start water filling the boiler drum through 30% control valve and maintain the drum level up to 30%.
. Start the Ash handling plant prior to light up the Boiler. Then start all hoppers RAV.
• Ensure bag filter main damper is closed & bypass damper is open
. Maintain the drum level about 40%.
• Drum vent, super heater vent and main steam line
drain should be kept open.
. Start wood firing by spraying small quantity of diesel & slowly raise the furnace temperature
• At furnace temperature > 150 deg C start ID & FD fans at minimum speed
⚫ Close drum air vent at 2.5 kg/cm2
⚫ At 3 kg/cm2, gibe blow down to CBD, IBD & bottom headers one by one for 30 sec to 45 seconds
• At pressure > 4 kg/cm2, open start up vent 10% initially & close the top header drain valves & go on increasing the pressure
• At furnace temperature around 250 deg C, start coal feeding by starting SA fan
• Now slowly increase fuel feeding & FD air
• When boiler pressure reaches 6 kg/cm2 & 150 deg C, charge the main steam line. Before charging the main steam line, open all the drains at 100% and warm up vents at minimum opening and then open the MSSV bypass valve.
• Start HP & LP dosing and maintain recommended drum water parameters of boiler. Keep the CBD at minimum opening to maintain recommended residual PO4 & conductivity of drum water
. Check & record thermal expansion of boiler pressure parts and record the bearings temperature & vibrations of auxiliary equipment's associated with Boiler
. After ensured all condensate removed & color less steam comes through drains, keep all the drains in crack position, then open main steam stop valve and close the bypass steam valve
⚫ At Boiler pressure 9 kg/cm2 & temperature 180 deg C, charge Deaerator & SCAPH through PRDSH
. At flue gas temperature > 180 deg C take bag filter into line
• Observe seal air pressure, conveying air vessel pressure of AHP is normal.
Slop firing:
• Ensure sufficient quantity of slop with required brix is available in slop tank
• Ensure tank coil heater & steam tracing lines are charged & tank slop temperature is 70 to 80 deg C • Ensure slop pumps are healthy & agitator is
running condition
• After ensuring above all are normal, start slop transfer pumps & keep slop in recirculation mode for at least 2 to 3 hours before taking into boiler
. As the Boiler reaches 50 to 60% of MCR & furnace temperature is 450 to 500 deg C open the atomizing steam line, slowly introduce the slop into furnace by opening SOV
• Note: Before introducing slop into nozzle, keep open the steam connection line provided with respective nozzle.
• Quantity of slop fired at MCR is 3.91 TPH & slop quantity should be reduced as the load demand reduces
• Always maintain 20 to 25% supporting fuel on heat
basis. Never start the Boiler with slop
⚫ During slop firing ensure supplement fuel is supplying continuously to avoid clinker
• The soot blowers provided in economizer, evaporators are operated once in a shift & wall blowers twice in a shift
Pre-checks
• Ensure DM water storage tank, feed tank & Deaerator level are normal
• Ensure availability of start up fuel (wood) & main fuel (coal) and power supply with DG backup
• Ensure maintenance & trial runs (healthiness) of all equipment including fuel handling, ash handling/ auxiliaries, motorized valves, actuators, control valves and PRDS controls are completed successfully
• Ensure that all interlocks / protection and controls are checked & taken in line.
• Ensure expansion pointers are cleaned & tramps
are in good condition.
• Ensure Boiler manholes and flue gas path system manholes are boxed up.
• Ensure availability of chemical dosing system and
readiness of drum level gauge glass with
illuminator assembly.
• Ensure availability of cooling water, instrument air and service air.
• Ensure Coal bunker is filled with required level
. Ensure all rotary air lock valves of evaporator, economizer & bag filters are open
• Ensure healthiness of all dampers and keep them
in open/close marked positions as per requirement • Open all air releases/vent valves in boiler drum and open super heater header drains and its vent valves.
• Ensure all boiler bottom ring header drains, blow down valves and main steam stop valves including its bypass valves are closed.
• Ensure Boiler feed pump's bearings oil level normal, minimum recirculation, balancing leak off valves & suction valves are open, cooling water pressure normal.
Boiler start up
. Start the ACW pump, Instrument Air & Service Air Compressor
• Start BFP from control room. Ensure suction pressure, balancing pressure & discharge pressure normal. Bearing temperature & Vibrations normal. Ensure motor draws current normal & sound normal. Shut the BFP immediately if any abnormal condition and check thoroughly before restart.
. Start water filling the boiler drum through 30% control valve and maintain the drum level up to 30%.
. Start the Ash handling plant prior to light up the Boiler. Then start all hoppers RAV.
• Ensure bag filter main damper is closed & bypass damper is open
. Maintain the drum level about 40%.
• Drum vent, super heater vent and main steam line
drain should be kept open.
. Start wood firing by spraying small quantity of diesel & slowly raise the furnace temperature
• At furnace temperature > 150 deg C start ID & FD fans at minimum speed
⚫ Close drum air vent at 2.5 kg/cm2
⚫ At 3 kg/cm2, gibe blow down to CBD, IBD & bottom headers one by one for 30 sec to 45 seconds
• At pressure > 4 kg/cm2, open start up vent 10% initially & close the top header drain valves & go on increasing the pressure
• At furnace temperature around 250 deg C, start coal feeding by starting SA fan
• Now slowly increase fuel feeding & FD air
• When boiler pressure reaches 6 kg/cm2 & 150 deg C, charge the main steam line. Before charging the main steam line, open all the drains at 100% and warm up vents at minimum opening and then open the MSSV bypass valve.
• Start HP & LP dosing and maintain recommended drum water parameters of boiler. Keep the CBD at minimum opening to maintain recommended residual PO4 & conductivity of drum water
. Check & record thermal expansion of boiler pressure parts and record the bearings temperature & vibrations of auxiliary equipment's associated with Boiler
. After ensured all condensate removed & color less steam comes through drains, keep all the drains in crack position, then open main steam stop valve and close the bypass steam valve
⚫ At Boiler pressure 9 kg/cm2 & temperature 180 deg C, charge Deaerator & SCAPH through PRDSH
. At flue gas temperature > 180 deg C take bag filter into line
• Observe seal air pressure, conveying air vessel pressure of AHP is normal.
Slop firing:
• Ensure sufficient quantity of slop with required brix is available in slop tank
• Ensure tank coil heater & steam tracing lines are charged & tank slop temperature is 70 to 80 deg C • Ensure slop pumps are healthy & agitator is
running condition
• After ensuring above all are normal, start slop transfer pumps & keep slop in recirculation mode for at least 2 to 3 hours before taking into boiler
. As the Boiler reaches 50 to 60% of MCR & furnace temperature is 450 to 500 deg C open the atomizing steam line, slowly introduce the slop into furnace by opening SOV
• Note: Before introducing slop into nozzle, keep open the steam connection line provided with respective nozzle.
• Quantity of slop fired at MCR is 3.91 TPH & slop quantity should be reduced as the load demand reduces
• Always maintain 20 to 25% supporting fuel on heat
basis. Never start the Boiler with slop
⚫ During slop firing ensure supplement fuel is supplying continuously to avoid clinker
• The soot blowers provided in economizer, evaporators are operated once in a shift & wall blowers twice in a shift
Subscribe to:
Posts (Atom)
STEAM TURBINE STANDARD OPERATING PROCEDURE
Steam Turbine standard operating procedures (SOPs) Lube oil system operation Pre-checks • Ensure lube oil tank level is normal • Ensure l...
-
Basics of 4-20mA Current Loop The 4-20 mA current loop is a very robust sensor signaling standard. Current loops are ideal for data transmi...
-
Rivets – Types, Failures Of Riveted Joint, Terms Used In Riveting Rivets – Types, Failures Of Riveted Joint, Terms Used In Riveting Rivets ...
-
What are Analog and Digital Signals? Differences, Examples What is a Signal? Gestures, actions, sounds, expressions tell us some information...