Steam Turbine standard operating procedures (SOPs)
Lube oil system operation
Pre-checks
• Ensure lube oil tank level is normal • Ensure lube oil pumps are healthy to operate
• Ensure lube filter & cooler are in service
• Ensure lube oil inlet and outlet valve provided at
filters & coolers are open Ensure cooling water inlet & outlet valves
provided for oil coolers are in closed condition
• Ensure suction & discharge valve of the pumps are in opened condition
Operation
. Start the oil pump (AOP)
• Ensure no abnormal sound & vibrations . Observe the discharge pressure
• Ensure header pressure is normal, if not adjust
with PRV or recirculation valve . Check the oil filter DP, if high change over the
filter
. Check overhead oil tank is getting filling
• Ensure lub oil is supplying to each bearing & adjust the oil pressure to each bearing as per
desired requirement . Maintain the oil temperature by adjusting
cooling water inlet & outlet valves.
Note: Keep open cooling water inlet valve 100% open & adjust the temperature by adjusting outlet valve
• Ensure the over head oil tank is full Keep stand by lube oil pump & EOP ready
Barring gear operation
• Ensure lube oil system is in service and oil is circulating at the bearings at a desired pressure
• Ensure barring gear motor is healthy to start & its all interlocks are in place
Engage the barring gear clutch . Start the barring gear motor
Observe the rotor is rotating at barring speed without increase in bearing vibrations & temperature
• Ensure there is no any abnormal sound
Cooling water system operation Pre-checks
• Ensure the cooling tower level is normal • Ensure cooling water pump is healthy to operate
& their protections & interlocks are in place
• Ensure cooling water pump (MCWP) suction
valve is open & discharge valve is closed
• Ensure all the field instruments are healthy & inline
• Ensure surface condenser inlet & outlet cooling
water line valves are open • Ensure Condenser water box vents are open
• Ensure cooling tower inlet cooling water line
valves are open
Operation
• Start the pump from DCS at 70% RPM
Open the discharge valve slowly • Observe discharge pressure is increasing
gradually
• Ensure the pump's vibration & bearing
temperatures are normal • After venting air from condenser water box
close the vent valves ⚫ Observe cooling water is falling in cooling water
• Increase the pump's speed as per requirement ⚫ Note down cooling water inlet & outlet water
temperature of condenser
. Start cooling tower fans one by one as per
requirement
Condensate system operation
• Ensure the hot well level is adequate. Otherwise make the hot well level with DM water
• Ensure the CEP is healthy & its all interlocks are in place
• Ensure pump's suction & discharge valves are open
• Ensure ejector & gland sealing steam condenser inlet & outlet cooling water line valves are open . Start the pump, ensure the water will flow from
ejector & Gland steam condenser (GSC)
• Ensure gland steam outlet control valve to deaerator is close & cooling water is recirculating through recirculating control valve
• If the hot well level increases, then GSC discharge valve can be opened
. Once the Turbine comes into line,GSC outlet control valve should be kept in auto mode to maintain hot well level
• Vacuum pulling & Vacuum killing
• Pre-checks
• Ensure auxiliary steam is available at desired pressure and temperature . Ensure vacuum breaker valve fitted on steam
condenser is closed • Ensure cooling water is circulating in the condenser and the turbine gland is charged fully
at 0.1 kg/cm2
• Ensure live steam line to ejector steam lines
drain are kept open • Ensure Hogger & main ejectors steam and air
valves are in closed condition
Vacuum pulling through hogger ejector
⚫ Charge the main steam line to ejector steam &
temperature control valve
• Ensure the rated pressure (10 kg/cm2) and temperature (220 deg C) for ejector vacuum pulling
. Once the rated parameters are reached open the steam valve of starting or hogger ejector . Observe the steam is vented to the atmosphere
⚫ Then open the ejector airline valve
• Observe vacuum inside the condenser increasing slowly and will reach 60 to 70% of rated vacuum within 20 minutes
SOP to put main ejector into line
• Ensure CEP is running
• Ensure cooling water inlet and outlet valves of
main ejector which is to be taken into line . Vent out air from water box of the ejector
• Then open the drain valve of inter condenser and after condenser of ejector
. Open the steam valve of after condenser ejector • Open the steam valve of inter condenser ejector
. Observe the condensate is drained out from both the condensers
Slowly open the air valve & observe the vacuum
is increasing
• When vacuum reaches rated, then stop the hogger or starting ejector
Vacuum killing or Taking out of main ejector
. Close the air valve of the ejector
. Close the steam valve of inter condenser
. Close the steam valve of after condenser
. Close the drain valves of after & inter condensers
. Close the cooling water inlet & outlet valve once the ejector is cooled
Subscribe to:
Post Comments (Atom)
STEAM TURBINE STANDARD OPERATING PROCEDURE
Steam Turbine standard operating procedures (SOPs) Lube oil system operation Pre-checks • Ensure lube oil tank level is normal • Ensure l...
-
Basics of 4-20mA Current Loop The 4-20 mA current loop is a very robust sensor signaling standard. Current loops are ideal for data transmi...
-
Rivets – Types, Failures Of Riveted Joint, Terms Used In Riveting Rivets – Types, Failures Of Riveted Joint, Terms Used In Riveting Rivets ...
-
What are Analog and Digital Signals? Differences, Examples What is a Signal? Gestures, actions, sounds, expressions tell us some information...
No comments:
Post a Comment